| Incorporation: |
| Maddhapara Granite
Mining Company Limited (MGMCL)
a company of Petrobangla
under the Ministry of Power,
Energy & Mineral Resources,
and Government of the
People’s Republic of Bangladesh was incorporated
on August 04, 1998 with a
paid up Capital of Taka 350 Crore under Company Act. Of
1994. |
| Objectives: |
| Maddhapara Granite
Mining Company Ltd. Was
established with multifold
responsibilities of
production of hardrock with
daily production capacity of
5,500 M. tons from the
underground mine, marketing
& selling of the produced
hardrock to different
Government entities e.g.
Roads & Highways, Water
Development Board, Port
Authority etc. as well as to
different private
organizations using rock for
the purposes of construction
for tiles, block production
using dust etc. |
| Main project of the
Company: Maddhapara Hardrock
Mining Project. |
| Salient Features of
Maddhapara Hardrock Mining
Project: |
| 1. |
Project title |
: |
Maddhapara Hardrock
Minin Project |
| 2. |
Location of the
Project |
: |
Vill: Maddhapara,
Thana: Parbatpur,
Dist : Dinajpur. |
|
3. |
Project objectives |
: |
The
main objective of
the Project is to
set up an
underground hardrock
mine at Maddhapara
Dinajpur. The mine
is designed to
produce 1.65 million
M. tons of hardrock
per annum to meet
the requirement of
flood control,
construction of
coastal and town
protection
embankment,
construction and
maintenance of
bridges, roads &
highways,
embankment, river
training, railway
ballast, high rise
buildings decoration
tiles and other
heavy duty
construction works. |
|
4. |
Depth of rock |
: |
124
meter from the
surface. |
|
5. |
Reserve & mine area |
: |
Reserve in the mine
area of 1.0 km × 1.2
km =1.2 km2 is 174
million tons |
|
6. |
Point load strength |
: |
24,000 PSI |
|
7. |
Annual Production |
: |
1.65 million tons. |
|
8. |
Life of the mine |
: |
Project
analysisbased on 41
years (including
development period)
but mine operation
life may be extended
for more than 70
years. |
|
9. |
Employment
opportunity |
: |
Direct -766,
Indirect – 10,000. |
|
10. |
Method of mine |
: |
Room & Pillar/
Sub-Level Drift
Stoping Method. |
|
11. |
Mode of Entry
(Length & dia. Of
shafts) |
: |
TwoVertical shafts
(The length of the
skip shaft is 380m &
cage shaft 330 m.
Inner dia of both
shafts is 5.0 m. and
distance between two
shafts is 85 m). |
|
12 |
Investment cost
(TK.
In lakh) |
: |
| Total |
Local |
F.E |
1024998.31
($ 197.889
m.) |
33110.06
($ 57.086
m.) |
69388.25
($ 140.803
m.) |
|
|
13. |
Foregin Source
(Supplier’s Credit) |
: |
US$
120.00 million. The
Korea South-South
Cooperation
Corporation (NAMNAM),
The Democratic
People’s Republic of
Korea. |
|
14. |
Local Source
(including Down
Payment of F.E.
component as cash
F.E) |
: |
By
GOB under ADP. |
|
15. |
Estimated production
cost |
: |
TK.
702 / ton
($12.095 / ton) |
|
16. |
Present sale price
(Commercial Product) |
: |
| Product |
Price |
| Boulder
( >300mm) |
US$
17.00 / Ton |
| Crushed
(5-20mm) |
US$
20.00 / Ton |
| Crushed
(20-40mm) |
US$
17.00 / Ton |
| Crushed
(40-60mm) |
US$
17.00 / Ton |
| Crushed
(60-80mm) |
US$
17.00 / Ton |
| Dust
(<5mm) |
US$
11.00 / Ton |
| + VAT
15% |
US$ 0.90 |
|
|
| Present Status: |
| Hardrock has been
extracted upto May 2009 a
sum of total of 5,83,857
metric ton and 3,23,748 M.
Ton of hardrock have already
been sold to different
organizations. The existing
crusher installed at the
project site can crush
hardrock 5 mm to 20 mm, 20
mm to 40 mm and 60 to 40 mm.
A 30 M. Ton and A 50 M Ton
capacity of truck Weighing
station have already been
installed at the project
site, by which the loaded
track are measured for
selling purpose of hardrock.. |
| Environment
Preservation: |
| The project will make a
significant contribution to
improve environment and
ecological balance by
replacing clay-burnt bricks
in construction works.
Present brick manufacturing
not only causes damage to
agricultural land but also
causes deforestation due to
indiscriminate use of
fire-wood in brick-field and
other purposes. The Project
will significantly reduce
production of bricks for
construction purposes and
thus held to check
deforestation. |
| The company has taken up
necessary steps to preserve
environment at the project
site during its
implementation project. The
mine water are being examine
regularly in order to
prevent pollution of
surrounding areas. Besides
various gases which evolved
due to blasting are measured
by gas analyzer regularly.
With the help of spraying
and water using local fan,
gases are diluted and
eliminated as such miners
are saved from any hazards. |
| In line of the
Government policy, 2818 nos.
of different varieties
saplings were planted in the
project area in order to
keep ecological balance. |
| Socio Economic
Development of the Project
Area: |
| The following Socio
Economic Development had
been established because of
the project: |
| Up-gradation &
completion of existing
Phulbari - Maddhapara Road
(13 km) by Roads and High
ways Department. The work
has already been completed. |
| Bhabanipur – Maddhapara
Railway line (14.5 km)
construction by Bangladesh
Railway. The Railway line
has already been completed. |
| Rangpur – Maddhapara –
Barapukuria – Syedpur (about
70 km) 33KV Power
Transmission line by
Bangladesh Power Development
Board (PDB). The
transmission line has
already been completed. |
| Maddhapara – Mithapukur
and Maddhapara –Badargonj
Road upgrading and
completion by Roads & High
Ways. Roads are being
implemented by Roads & High
ways. |
| The project will also
contribute in creation of
linkage industries,
infrastructural facilities,
direct and indirect job
opportunities for overall
socio-economic development
of the project area. |
| Human Resources
Development: |
| At present total
Manpower of the company
stands at which included 96
officers and 62 staffs. In
local and abroad various
types of training courses
have been organized to
develop the human resources
of company. 20 nos. of
officers have already been
trained in different
discipline of mining in DPR
of Korea. 320 nos. of mine
workers have been locally
trained by Korean Mine
experts. After completion of
the project they would be
employed in place of
Agreement with Supervisory.
23 nos. of officers Have
already been trained in
Poland under the
Supplementary Agreement with
Supervisory Consultancy. 57
officers had also been
trained up locally in
different courses from
different training institute
e.g. Academy for planning
and Development, TICI, IEB,
BPI, BIM, USAID etc. |