Home
   About Us
   Board of Directors
   Photo Gallery
   Tender Notice
   Contact

News

Links

  www.bangladesh.gov.bd
  www.petrobangla.org.bd
 
"This website is under construction !"

top
Incorporation:
Maddhapara Granite Mining Company Limited (MGMCL) a company of Petrobangla under the Ministry of Power, Energy & Mineral Resources, and Government of the People’s Republic of Bangladesh was incorporated on August 04, 1998 with a paid up Capital of Taka 350 Crore under Company Act. Of 1994.
Objectives:
Maddhapara Granite Mining Company Ltd. Was established with multifold responsibilities of production of hardrock with daily production capacity of 5,500 M. tons from the underground mine, marketing & selling of the produced hardrock to different Government entities e.g. Roads & Highways, Water Development Board, Port Authority etc. as well as to different private organizations using rock for the purposes of construction for tiles, block production using dust etc.
Main project of the Company: Maddhapara Hardrock Mining Project.
Salient Features of Maddhapara Hardrock Mining Project:
1. Project title : Maddhapara Hardrock Minin Project
2. Location of the Project : Vill: Maddhapara, Thana: Parbatpur, Dist : Dinajpur.
3. Project objectives : The main objective of the Project is to set up an underground hardrock mine at Maddhapara Dinajpur. The mine is designed to produce 1.65 million M. tons of hardrock per annum to meet the requirement of flood control, construction of coastal and town protection embankment, construction and maintenance of bridges, roads & highways, embankment, river training, railway ballast, high rise buildings decoration tiles and other heavy duty construction works.
4. Depth of rock : 124 meter from the surface.
5. Reserve & mine area : Reserve in the mine area of 1.0 km × 1.2 km =1.2 km2 is 174 million tons
6. Point load strength : 24,000 PSI
7. Annual Production : 1.65 million tons.
8. Life of the mine : Project analysisbased on 41 years (including development period) but mine operation life may be extended for more than 70 years.
9. Employment opportunity : Direct -766, Indirect – 10,000.
10. Method of mine : Room & Pillar/ Sub-Level Drift Stoping Method.
11. Mode of Entry
(Length & dia. Of shafts)
: TwoVertical shafts (The length of the skip shaft is 380m & cage shaft 330 m. Inner dia of both shafts is 5.0 m. and distance between two shafts is 85 m).
12 Investment cost
(TK. In lakh)
:
Total Local F.E
1024998.31
($ 197.889 m.)
33110.06
($ 57.086 m.)
69388.25
($ 140.803 m.)
13. Foregin Source              (Supplier’s Credit) : US$ 120.00 million. The Korea South-South Cooperation Corporation (NAMNAM), The Democratic People’s Republic of Korea.
14. Local Source
(including Down Payment of F.E. component as cash F.E)
: By GOB under ADP.
15. Estimated production cost : TK. 702 / ton ($12.095 / ton)
16. Present sale price
(Commercial Product)
:
Product Price
Boulder ( >300mm) US$ 17.00 / Ton
Crushed (5-20mm) US$ 20.00 / Ton
Crushed (20-40mm) US$ 17.00 / Ton
Crushed (40-60mm) US$ 17.00 / Ton
Crushed (60-80mm) US$ 17.00 / Ton
Dust (<5mm) US$ 11.00 / Ton
+ VAT 15% US$ 0.90
Present Status:
Hardrock has been extracted upto May 2009 a sum of total of 5,83,857 metric ton and 3,23,748 M. Ton of hardrock have already been sold to different organizations. The existing crusher installed at the project site can crush hardrock 5 mm to 20 mm, 20 mm to 40 mm and 60 to 40 mm. A 30 M. Ton and A 50 M Ton capacity of truck Weighing station have already been installed at the project site, by which the loaded track are measured for selling purpose of hardrock..
Environment Preservation:
The project will make a significant contribution to improve environment and ecological balance by replacing clay-burnt bricks in construction works. Present brick manufacturing not only causes damage to agricultural land but also causes deforestation due to indiscriminate use of fire-wood in brick-field and other purposes. The Project will significantly reduce production of bricks for construction purposes and thus held to check deforestation.
The company has taken up necessary steps to preserve environment at the project site during its implementation project. The mine water are being examine regularly in order to prevent pollution of surrounding areas. Besides various gases which evolved due to blasting are measured by gas analyzer regularly. With the help of spraying and water using local fan, gases are diluted and eliminated as such miners are saved from any hazards.
In line of the Government policy, 2818 nos. of different varieties saplings were planted in the project area in order to keep ecological balance.
Socio Economic Development of the Project Area:
The following Socio Economic Development had been established because of the project:
Up-gradation & completion of existing Phulbari - Maddhapara Road (13 km) by Roads and High ways Department. The work has already been completed.
Bhabanipur – Maddhapara Railway line (14.5 km) construction by Bangladesh Railway. The Railway line has already been completed.
Rangpur – Maddhapara – Barapukuria – Syedpur (about 70 km) 33KV Power Transmission line by Bangladesh Power Development Board (PDB). The transmission line has already been completed.
Maddhapara – Mithapukur and Maddhapara –Badargonj Road upgrading and completion by Roads & High Ways. Roads are being implemented by Roads & High ways.
The project will also contribute in creation of linkage industries, infrastructural facilities, direct and indirect job opportunities for overall socio-economic development of the project area.
Human Resources Development:
At present total Manpower of the company stands at which included 96 officers and 62 staffs. In local and abroad various types of training courses have been organized to develop the human resources of company. 20 nos. of officers have already been trained in different discipline of mining in DPR of Korea. 320 nos. of mine workers have been locally trained by Korean Mine experts. After completion of the project they would be employed in place of Agreement with Supervisory. 23 nos. of officers Have already been trained in Poland under the Supplementary Agreement with Supervisory Consultancy. 57 officers had also been trained up locally in different courses from different training institute e.g. Academy for planning and Development, TICI, IEB, BPI, BIM, USAID etc.
 

Home | About Us | Board of Directors | Photo Gallery | Tender Notice | Contact

© MGMCL 2006-2007, All rights reserved.